 How To Create SCRUM Burn-down Charts in Microsoft Office Project Server 2007 Minimize
This how to document shows how to create SCRUM Burn-down charts using the Microsoft Office Project Server 2007 data anaysis views (OLAP). 

It gives step by step details on creation of the Sprint ID fields and lookup tables. It also show the details of creating the new dimension(s) needed and the new calculated measures for Remaining Planned Work and Remaining Actual Work burn downs.

SCRUM Burn Down Chart.gif
This view answers questions like:
  • Sprint progress - how is the team doing toward meeting their Sprint goal?
  • Release progress - will the release be on time with the quality and functionality desired?
  • Product progress - how is the product filling out compared to what's needed?

     